ROAD TOWN, British Virgin Islands, Feb. 26, 2025 (GLOBE NEWSWIRE) -- Aura Minerals Inc. (TSX:ORA) (B3: AURA33) (OTCQX:ORAAF) ("Aura" or the "Company") announces that it has filed its audited consolidated financial statements and management discussion and analysis (together, "Financial and Operational Results") for the period ended December 31, 2024. The full version of the Financial and Operational Results can be viewed on the Company's website at www.auraminerals.com or on SEDAR+ at www.sedarplus.ca. All amounts are in thousands of U.S. dollars unless stated otherwise.

Rodrigo Barbosa, President, and CEO of Aura, commented: "In 2024, we doubled our EBITDA to US$267 million, with average gold prices of nearly US$2,400 / Oz—well below current levels—while keeping costs firmly under control with our all-in sustaining costs (AISC) at US$1,320/Oz, below the industry average. Almas operation overcame a challenging first half to deliver an outstanding full-year performance, producing 54,129 Oz at an AISC of US$1,139/Oz. This success sets a strong foundation for Borborema, which remains on track and on budget for its 2025 startup, promising higher average production and costs below our average AISC.

Additionally, we bolstered our portfolio with the acquisition of a world-class deposit and achieved significant exploration progress. In all, 2024 marked another year of production growth, up 18% at constant metal prices, and advancement of new projects with US$159 million invested in growth for future years, all while delivering returns to shareholders through dividends and ongoing share buybacks, yielding 9.2% in the LTM. Remarkably, while expanding operations, ramping up new mines, and building another mine, our safety record remains among the best in the industry, with only one non-severe lost-time incident (LTI) in two years"

Q4 2024 and 2024 Financial and Operational Highlights:

(US$ thousand):

 For the three

months ended

December 31,

2024
For the three

months ended

December 31,

2023
For the twelve

months ended

December 31,

2024
For the twelve

months ended

December 31,

2023
Total Production1 (GEO)66,473 69,194 267,232 235,856 
Sales2 (GEO)69,341 68,571 269,833 233,923 
Net Revenue171,517 124,322 594,163 416,894 
Adjusted EBITDA79,319 40,893 266,768 134,107 
AISC per GEO sold1,373 1,311 1,320 1,325 
Ending Cash balance270,189 237,295 270,189 237,295 
Net Debt188,079 85,165 188,079 85,165 
Income/(Loss) for the period16,644 (5,908)(30,271)31,880 
Adjusted Net Income24,636 19,926 81,547 58,602 

(1)   Considers capitalized production

(2)   Does not consider capitalized production

________________________

1 AISC is a non-GAAP financial measure with no standardized meaning under IFRS, and therefore may not be comparable to similar measures presented by other issuers. For further information and detailed reconciliations to the most directly comparable IFRS measures, see Section 17: Non-GAAP Performance Measures in this MD&A.

Dividends and Buybacks

In March, Aura announced simultaneous buyback programs for Ordinary Shares on the Toronto Stock Exchange (TSX) and Brazilian Depositary Receipts (BDRs) on B3. As of December 31, 2024, the Company had repurchased 1,082,497 common shares of its Brazilian Depositary Receipts2 and 183,710 under the Normal Course Issuer Bidder program and canceled 116,948 shares from the total repurchased. To date, US$13,576 were invested in shares and BDRs buybacks.

________________________

2 Each common share is equivalent to 3 Brazilian Depositary Receipts.

Safety

Borborema construction

As of the date of this MD&A, the Borborema Project construction is on track to be completed in the first quarter of 2025. Construction capex is 100% committed. Significant developments include the conclusion of the Main Substation, Power Line, Mechanical assembly of the Crushing Area and the CIL area. The mine pre-stripping is ongoing according to the plan and moved a total of 5.7Mt. The project currently employs 2,184 direct and indirect personnel.

Bluestone Acquisition Closing

On January 13, 2025, Aura completed the previously announced plan of arrangement with Bluestone Resources (the "Acquisition"). The Acquisition includes a high-grade gold deposit with approximately2.4 million ounces of gold and 10.4 ounces of silver (41 Mt at average grade 1.8 g/t Au and 7.9 g/t Ag) in Measured category and approximately 700 thousand ounces of gold and 3.0 million ounces of silver (22.6 Mt at average grade of 1.0 g/t Au and 4.2 g/t silver) in Indicated category of mineral resources and an advanced renewable energy project. In the coming months, the Company will conduct a review of the feasibility study and evaluate alternatives to optimize scale, risk, and return profile of the project. Concurrently, Aura will implement Aura 360 concept, adhering to the highest environmental and social standards, in preparation to begin construction. Additionally, the geothermal energy project at Cerro Blanco, which has the potential to generate up to 50MW, offers a distinctive opportunity to utilize renewable energy and possibly sell any excess to Guatemala.

Guidance 2024 Achievement:

The Company achieved its guidance for 2024, including production, cash cost, All-In Sustaining Cost (AISC), and capital expenditures, as demonstrated by the results of the year.

Gold equivalent thousand ounces

('000 GEO) production - 2024
 Low - 2024High - 20242024 A%2024 A at

Guidance Prices
%
Minosa (San Andrés)607578104% - 130%78104% - 130%
Apoena (EPP)46563766% - 81%3766% - 81%
Aranzazu941089890% - 104%10798% - 114%
Almas455354103% - 121%54103% - 121%
Total24429226791% - 109%27694% - 113%



Cash Cost per equivalent ounce

of gold produced - 2024
 Low - 2024High - 20242024 AΔ LowΔ High2024 A at Guidance PricesΔ LowΔ High
Minosa (San Andrés)1,1201,2881,1260%-13%1,1260%-13%
Apoena (EPP)1,1821,3001,1891%-9%1,1891%-9%
Aranzazu8261,00996517%-4%8867%-12%
Almas9321,0259502%-7%9502%-7%
Total9841,1401,0416%-9%1,0093%-11%
         
         
AISC per equivalent ounce

of gold produced - 2024
 Low - 2024High - 20242024 AΔ LowΔ High2024 A at Guidance PricesΔ LowΔ High
Minosa (San Andrés)1,2161,3981,205-1%-14%1,205-1%-14%
Apoena (EPP)1,5881,7471,83315%5%1,83315%5%
Aranzazu1,0891,3311,30820%-2%1,20110%-10%
Almas1,1791,2971,139-3%-12%1,139-3%-12%
Total1,2901,4591,3202%-10%1,279-1%-12%



Capex (US$ million) - 2024
 Low - 2024High - 20242024 A%
Sustaining

37

43

36

83% - 96%
Exploration

7

8

8

102% - 119%
New projects + expansion144

169

137

81% - 95%
Total188

219

181

82% - 96%



Guidance 2025

The Company's updated gold equivalent production, AISC and cash operating cost per gold equivalent ounce sold, and CAPEX guidance for 2025 are detailed below.

Production

The table below details the Company's updated GEO production guidance for 2025 by business unit:

  Gold equivalent thousand ounces

('000 GEO) production - 2025


 
  Low - 2025High - 2025 
 Minosa (San Andrés)6473 
 Apoena (EPP)2932 
 Aranzazu8897 
 Almas5158 
 Borborema3340 
 Total266300 

For current guidance, the Company considered: Copper price = $4.29/lb; Gold Price = $2,634,41/oz; Silver Price = $31.66/oz

2025 Production Guidance:

All in all, the 2025 production guidance expects production of 266-300 kGEO, represents an increase of up to 33k GEO when compared to 2024 at current prices and up to 37k GEO at constant metal prices.

Cash Costs

The table below shows the Company's cash operating costs per GEO sold guidance for 2025 by Business Unit:

  Cash Cost per equivalent ounce

of gold produced - 2025


 
  Low - 2025High - 2025 
 Minosa (San Andrés)1,1081,219 
 Apoena (EPP)1,2581,384 
 Aranzazu1,0291,132 
 Almas1,0131,114 
 Borborema1,0841,232 
 Total1,0781,191 
 Total ex-Apoena1,0551,167 
     

2025 Cash Cost Guidance:

All In Sustaining costs

The table below shows the Company's all-in sustaining costs per GEO sold guidance for 2025 by Business Unit:

  AISC per equivalent ounce

of gold produced - 2025


 
  Low - 2025High - 2025 
 Minosa (San Andrés)1,2631,364 
 Apoena (EPP)2,4252,619 
 Aranzazu1,3481,455 
 Almas1,1131,202 
 Borborema1,1131,304 
 Total1,3741,492 
 Total ex-Apoena1,2411,353 
     

2025 All-In Sustaining Cost Guidance:

Capex:

The table below shows the breakdown of estimated capital expenditures by type of investment:

  Capex (US$ million) - 2025

 
  Low - 2025High - 2025 
 Sustaining4047 
 Exploration1013 
 New projects + Expansion99106 
 Total149167 
     

2024 and Q4 2024 Earnings Call

The Company will hold an earnings conference call on Thursday, February 27, 2025, at 8:00 AM (Eastern Time). To register and participate, please click the link below.

Date: February 27, 2025

Time: 8:00 AM (New York and Toronto) | 10:00 AM (Brasília)

Access Link: Click here.

Key Factors

The Company's future profitability, operating cash flows, and financial position will be closely related to the prevailing prices of gold and copper. Key factors influencing the price of gold and copper include, but are not limited to, the supply of and demand for gold and copper, the relative strength of currencies (particularly the United States dollar), and macroeconomic factors such as current and future expectations for inflation and interest rates. Management believes that the short-to-medium term economic environment is likely to remain relatively supportive for commodity prices but with continued volatility.

To decrease risks associated with commodity prices and currency volatility, the Company will continue to evaluate and implement available protection programs. For additional information on this, please refer to the AIF.

Other key factors influencing profitability and operating cash flows are production levels (impacted by grades, ore quantities, process recoveries, labor, country stability, plant, and equipment availabilities), production and processing costs (impacted by production levels, prices, and usage of key consumables, labor, inflation, and exchange rates), among other factors.

Non-GAAP Measures

In this press release, the Company has included Adjusted EBITDA, cash operating costs per gold equivalent ounce sold, AISC and net debt which are non-GAAP measures. These non-GAAP measures do not have any standardized meaning within IFRS and therefore may not be comparable to similar measures presented by other companies. The Company believes that these measures provide investors with additional information which is useful in evaluating the Company's performance and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The below tables provide a reconciliation of the non-GAAP measures presented:

Reconciliation from Income for the Quarter for EBITDA and Adjusted EBITDA (US$ thousand):
 
 For the three

months ended

December 31,

2024
For the three

months ended

December 31,

2023
For the twelve

months ended

December 31,

2024
For the twelve

months ended

December 31,

2023
Profit (loss) from continued and discontinued operation16,644 (5,908)(30,271)31,880 
Income tax (expense) recovery16,383 1,598 52,971 18,798 
Deferred income tax (expense) recovery23,982 (6,049)29,720 (12,372)
Finance costs9,791 36,874 151,679 49,379 
Other gains (losses)315 5,077 1,267 (659)
Depreciation13,534 9,301 62,732 47,082 
EBITDA80,649 40,893 268,098 134,107 
Impairment- - - - 
ARO Change(1,330)- (1,330)- 
Adjusted EBITDA79,319 40,893 266,768 134,107 
     
 
Reconciliation from the consolidated financial statements to cash operating costs per gold equivalent ounce sold (US$ thousand):
     
 For the three

months ended

December 31,

2024
For the three

months ended

December 31,

2023
For the twelve

months ended

December 31,

2024
For the twelve

months ended

December 31,

2023
Cost of goods sold(90,418)(84,186)(342,893)(290,877)
Depreciation14,270 9,844 61,847 46,816 
COGS w/o Depreciation(76,148)(74,342)(281,046)(244,061)
Gold Equivalent Ounces sold69,341 68,571 269,833 233,923 
Cash costs per gold equivalent ounce sold1,098 1,084 1,042 1,043 
     
 
Reconciliation from the consolidated financial statements to all in sustaining costs per gold equivalent ounce sold (US$ thousand):
     
 For the three

months ended

December 31,

2024
For the three

months ended

December 31,

2023
For the twelve

months ended

December 31,

2024
For the twelve

months ended

December 31,

2023
Cost of goods sold(90,418)(84,186)(342,893)(290,877)
Depreciation14,270 9,844 61,847 46,816 
COGS w/o Depreciation(76,148)(74,342)(281,046)(244,061)
Capex w/o Expansion9,212 10,378 43,937 44,481 
Site G&A6,124 1,687 14,024 8,217 
Lease Payments3,712 3,473 17,202 13,109 
Sub-Total    
Gold Equivalent Ounces sold69,341 68,571 269,833 233,923 
All In Sustaining costs per ounce sold1,373 1,311 1,320 1,325 



Reconciliation Net Debt (US$ thousand):
 For the three

months ended

December 31,

2024
For the three

months ended

December 31,

2023
Short Term Loans82,007 82,865 
Long-Term Loans361,097 250,724 
Plus / (Less): Derivative Financial Instrument for Debentures15,164 (11,129)
Less: Cash and Cash Equivalents(270,189)(237,295)
Less: Restricted cash- - 
Less: Short term investments- - 
Net Debt188,079 85,165 
   

About Aura 360° Mining

Aura is focused on mining in complete terms – thinking holistically about how its business impacts and benefits every one of our stakeholders: our company, our shareholders, our employees, and the countries and communities we serve. We call this 360° Mining.

Aura is a mid-tier gold and copper production company focused on operating and developing gold and base metal projects in the Americas. The Company has 4 operating mines including the Aranzazu copper-gold-silver mine in Mexico, the Apoena (EPP) and Almas gold mines in Brazil, and the Minosa (San Andres) gold mine in Honduras. The Company's development projects include Borborema and Matupá both in Brazil. Aura has unmatched exploration potential owning over 630,000 hectares of mineral rights and is currently advancing multiple near-mine and regional targets along with the Aura Carajas copper project in the prolific Carajás region of Brazil.

Forward-Looking Information

This press release contains "forward-looking information" and "forward-looking statements", as defined in applicable securities laws (collectively, "forward-looking statements") which may include, but is not limited to, statements with respect to the activities, events or developments that the Company expects or anticipates will or may occur in the future. Often, but not always, forward-looking statements can be identified by the use of words and phrases such as "plans," "expects," "is expected," "budget," "scheduled," "estimates," "forecasts," "intends," "anticipates," or "believes" or variations (including negative variations) of such words and phrases, or state that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be achieved.

Known and unknown risks, uncertainties and other factors, many of which are beyond the Company's ability to predict or control, could cause actual results to differ materially from those contained in the forward-looking statements. Specific reference is made to the most recent Annual Information Form on file with certain Canadian provincial securities regulatory authorities for a discussion of some of the factors underlying forward-looking statements, which include, without limitation, volatility in the prices of gold, copper and certain other commodities, changes in debt and equity markets, the uncertainties involved in interpreting geological data, increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and exchange rate fluctuations, general economic conditions and other risks involved in the mineral exploration and development industry. Readers are cautioned that the foregoing list of factors is not exhaustive of the factors that may affect the forward-looking statements.

All forward-looking statements herein are qualified by this cautionary statement. Accordingly, readers should not place undue reliance on forward-looking statements. The Company undertakes no obligation to update publicly or otherwise revise any forward-looking statements whether as a result of new information or future events or otherwise, except as may be required by law. If the Company does update one or more forward-looking statements, no inference should be drawn that it will make additional updates with respect to those or other forward-looking statements.

Financial Outlook and Future-Oriented Financial Information

To the extent any forward-looking statements in this press release constitute "financial outlooks" within the meaning of applicable Canadian securities legislation, such information is being provided as certain estimated financial metrics and the reader is cautioned that this information may not be appropriate for any other purpose and the reader should not place undue reliance on such financial outlooks. Such information was approved by the company's Board of Directors on February 26, 2025. Financial outlooks, as with forward-looking statements generally, are, without limitation, based on the assumptions and subject to various risks as set out herein. The Company's actual financial position and results of operations may differ materially from management's current expectations and, as a result, may differ materially from values provided in this press release.



For more information, please contact:
Investor Relations
ri@auraminerals.com
www.auraminerals.com

Primary Logo